MAN Production Planning (PP)

More about handling units in Production Planning perspective

I. Maintaining Handling units

1. HU02

To Create, Change handling units

MAN Production Planning (PP)

2. HU03

To display handling units

MAN Production Planning (PP)

3. HUMO

Search HU by using any of fields in the selection screen of HU monitor transaction

MAN Production Planning (PP)

Also from HUMO, HU can be locked/unlocked.
HU postings can also be executed from HUMO and VLMOVE as well.

4. MMBE

Enter material and plant and execute, go to environment à Handling unit

MAN Production Planning (PP)

After opening the HU by any of above ways, all the details of HU can be maintained.

MAN Production Planning (PP)

II. Reverse goods movements with HU

1. HUCANC

Put the HU number and simulate (run in test mode)

MAN Production Planning (PP)

MAN Production Planning (PP)

If its success, you can click on execute to reverse goods movement of this HU

MAN Production Planning (PP)

This reversed HU cannot be used by other orders, as this will be still assigned to the production order. COPAWA needs to be executed after this step if HU needs to be used in another order.

III. PACK/UNPACK/REPACK

1. Pack HU – HU02

Enter material, handling unit details and click on “Pack” button to pack the HU.

MAN Production Planning (PP)

2. Unpack/Empty HU – HU02

In case of any damages to HU unpack/Empty the old HU and repack the material into new HU.

MAN Production Planning (PP)

or

MAN Production Planning (PP)

MAN Production Planning (PP)

3. Repack HU – HU02

Select material, new handling unit and click on pack HU button. You can delete old HU if not required.

MAN Production Planning (PP)

MAN Production Planning (PP)

And save the transaction.

IV. HU goods issue

After creating and confirming the production order, follow below steps to pack order components

1. COPAWA

Enter Production order and click Enter

MAN Production Planning (PP)

Select component to be picked and click on Copy

MAN Production Planning (PP)

It will be copied to materials tab

MAN Production Planning (PP)

Select packing material and component and click on Pack

Save

Other options in COPAWA

Assign HU – Manually created HU can be added here. For example HU created in HU01.

MAN Production Planning (PP)

Assign – Click on this button to assign HU to production order

No Part. GI allowed – Partial GI for this HU will not be allowed if this is selected

Partial GI allowed – Partial GI is allowed for HU

Delete HU assignment – Delete the HU assignment to this order, so that it can be used for other order.

MAN Production Planning (PP)

Delete Assignment – Click on this button to delete HU assignment to production order

2. COWBHUWA

Enter Order Number and click on “Propose HU”. All the HU’s assigned to order will be displayed.

MAN Production Planning (PP)

Selected the component to be issued and click on “Partial GI”

MAN Production Planning (PP)

Enter the partial amount of quantity to be issued and hit enter

Save

Other option of partial GI

Previous/next HU – Display of further HUs that are selected for the partial goods issue posting

Superior/subordinate HU – Display of the hierarchically lower HUs that are packed in an HU or display of the hierarchically higher HU.

No GI posting – This option will set the content quantity of the selected HU to zero. A partial goods issue posting is not possible.