This document explains the integration points between PP and QM modules.

Integration Points

1. In process inspection during Production

2. Inspection after Goods Receipt for Production order

In process inspection during Production:

During production it is required to check the product at once or at regular intervals like for every one hour or after producing certain qty like 100 KG or after changing the equipment part etc.. for this In process inspection during Production functionality is used..

we will see the settings needed for this…

First activate Inspection type 03 in material master in Quality management view as shown below….

MAN Production Planning (PP), Manufacturing

Now go to routing and select the operation for which inspection is done and click on the button Inspection characteristics

Now assign the Master Inspection Characteristics as shown below

MAN Production Planning (PP), Manufacturing

Now save the routing…

Now create Production order for material as shown below..

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

Now save the order

MAN Production Planning (PP), Manufacturing

Now release the Production order.. during release system will generate the inspection lot as shown below…..

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

Now for this inspection lot you can carry out Results recording and Usage decision….there is no stock posting in this case…

If it is required to carry out inspection at some regular intervals check the below document for the settings and flow….

Inspection after Goods Receipt for Production order :

It is required to check the product after completion of production process. for this inspection at GR for production order functionality is used…

Activation of Inspection Type 04 in the quality management view in the material master of the Material (mm02) as shown below…

MAN Production Planning (PP), Manufacturing

We need to maintain the below QM relevant master data after this…

Master Inspection Characteristics.

Sampling Procedures

Inspection Plans – QP01

Now create the Production order and release the order….

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

Now do the goods receipt for the Production Order through MB31…

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing
MAN Production Planning (PP), Manufacturing

Now check in mmbe.. Stock will be in quality inspection and inspection lot is generated….

MAN Production Planning (PP), Manufacturing

check for the inspection lot as shown below in QA32…

MAN Production Planning (PP), Manufacturing

MAN Production Planning (PP), Manufacturing

after completion quality transaction Results Recording, Usage decision and stock posting, stock is transferred to unrestricted use if approved or to blocked stock if rejected…