Introduction
Sap Pooled Asset Complete Configuration is demonstrated in below link
https://www.sapspot.com/detail-pool-asset-configuration-steps/
Read More: SAP PP Certification Preparation Guide
Execution steps to capturing the cost & scheduling process is explained in below process steps
Process steps
Creation of Notification for pooled asset request as Notification Type (MF) through Tcode IW21

Fill up the user & Requester field with appropriate sap user id


Please fill up settlement order or cost center to settle the handling or running cost of equipment.

Please fill up maintenance plant & Location details

Save to generate a notification
Enter Tcode PAM03 to open the PM planning Board by below input & click on execute button


Now Notification need to be allocated to corresponding equipment by dragging and dropping in planning board and colour will be changed to yellow

Then reserve the equipment by clicking on yellow Box and reserve for use so that colour will be changed to Red



Than issue the Equipment by clicking on red box


Enter the odometer reading than click on create button so that automatically measuring point document will be updated. And box colour will be changed to green.

At the time of returning of equipment first double click on green box than enter the odometer reading by clicking return button than click on create button so that automatically measuring point document will be updated. And box colour will be changed to single black line for settlement.



Then click on this blue bar to settle the cost